DFCC Progress

Progress of the Dedicated Freight Corridor Corp. (DFCC) Projects

Project Detailed Overview

Title

Value

Comments

Total length of Eastern & Western DFC (Except Sonnagar-Dankuni section)

2843 Kms

  • Eastern - 1337 Kms

  • Western - 1506 Kms

Target for completion

June 2022

Total Estimated cost (Including Land)

Rs. 95,238 Cr

Cumulative CAPEX up to 30.11.2020

Rs. 67,971 Cr

Financial progress (Works)

62%

Funding

Eastern corridor

Stretch

Agency

Funding

Ludhiana-Mughalsarai (1200 km)

World Bank

US $1.775 billion

Mughalsarai-Sonnagar (137 km)

Indian Railways

Rs. 3679 Cr

Dankuni-Sonnagar (538 km)

Public Private Partnership (PPP)

Rs. 15,926 Cr

Western corridor

Stretch

Agency

Funding

Dadri-JNPT (1506 km) (Phase-I & II)

JICA

Rs. 38,722 Cr

Land acquisition

Section

Total scope

(Ha)

Notification u/s

20A (Ha)

Award u/s

20F (Ha)

Easter Corridor (without Sonnagar-Dankuni)

4619

4618

4617

Western Corridor

6000

6000

5991

Total

10619

10618

10608

Sonnagar-Dankuni section (PPP)

1194

1120

1040

Status

WDFC

Financial progress of the WDFC is 61%

Section

Length (Km)

Commission target

Dadri-Rewari

127

Mar 2022

Rewari-Palanpur

306+335

Partial route Commissioned

Palanpur-Makarpura

308

Mar 2022

Makarpura-Sachin

135

June 2022

Sachin-Vaitarna

186

June 2022

Vaitarna-JNPT

109

June 2022

EDFC

Section

Length (Km)

Commission target

Bhaupur-Khurja

351

Commissioned

Bhaupur - Sujatpur

Sujatpur - DDU

180

222

Dec 2021

June 2022

DDU-Ganjkhwaja

Ganjkhwaja-Chirailpathu

37

100

Dec 2021

Mar 2021

Khurja-Dadri

46

June 2021

Khurja-Pikhani

222

June 2022

Pilkhani-Ludhiana

179

June 2022

Sources

DFC

Dadri to JNPT

DMIC

Clusters proposed relating to Dighi port
Existing industrial clusters and networks